Burnham Drive & Harborview Drive ½-width Roadway Improvements Project - Design and Permiting

Project Description

The City is working with consultant David Evans and Associates in completing the preliminary design and permitting associated with  street  improvements along Burnham Drive in compliance with City of Gig Harbor Public Works Standards.  The project consists of adding bike lanes, sidewalk, planter strip, and pedestrian lighting on the east side of the roadway between Austin Street and Harbor Hill Drive.  It also includes incorporating  LID stormwater elements to reduce runoff, providing flow control, and providing stormwater quality treatment.  


Project Schedule

  • City will be holding a formal public comment period on November 9

Primary Project Contact

Marcos McGraw, Project Engineer at mcgrawm@cityofgigharbor.net

Lift Station #6 Replacement - Ryan Street

Project Description

Replacement of the underground lift station at the existing site.


Project Schedule

  • Virtual Open House held: 9/16/20 from 4:00 pm - 5:30 pm.
  • Final design and permitting underway
  • Construction planned for early summer 2021 with completion anticipated by the end of 2021

Primary Project Contact

Trent Ward, PE, City Engineer at wardt@cityofgigharbor.net


Stinson Avenue Overlay (Grandview to Rosedale) and Roundabout at Rosedale

Project Description

This grant-funded project consists of constructing approximately 2,700 LF of pavement overlay along Stinson Avenue between Rosedale Street and Pioneer Way. The project will construct a mini roundabout at Stinson/Rosedale and provide an HMA overlay and upgrade the existing non-compliant curb ramps to ADA standards.


Project Schedule

  • Construction planned for early 2021 with completion anticipated by early fall 2021

Primary Project Contact

Aaron Hulst, PE, Senior Engineer at hulsta@cityofgigharbor.net


Stinson Avenue/Harborview Drive Intersection Improvements

Project Description

This grant-funded project consists of constructing a full intersection design of a roundabout, that includes adding additional new parking stalls to Eddon Boat. 


Project Schedule

  • Construction planned for early 2021 with completion anticipated by early fall 2021

Primary Project Contact

Aaron Hulst, PE, Senior Engineer at hulsta@cityofgigharbor.net